Construction Progress Update: July 2023

Line
News & Updates

We’re pleased to advise our delivery partner Robson Civil continues to make excellent progress at McFarlanes Rise.

Recent construction milestones include:

  • 30% of topsoil completed
  • 70% of cut/fill completed
  • 90% of the 1.4km of sewer infrastructure installed

The following activities will soon commence:

  • Kerb and gutter installation
  • 1.1km of services (electrical, gas, water, NBN)
  • 700m of water reticulation
  • Road sub-base and base installation
  • Road asphalt and primer seal

Land registration is on track for the first quarter (Jan to Mar) of 2024.

Enquire Now

For more information on plans and pricing, please complete the form below.

1300 673 181

Privacy Policy / Disclaimer
© New Horizon Properties 2024. All rights reserved.

Brand & Marketing by Delivery.net.au

Enquire Now

For more information on plans and pricing, please complete the form below.

Disclaimer

New Horizon Properties do not guarantee, warrant or represent that the information contained on this website, advertising and marketing material is correct. Any interested parties should make their own enquiries as to the accuracy of the information. We exclude all inferred or implied terms, conditions and warranties arising out of this document and any liability for loss or damage arising there from.

Privacy Policy